No-Voltage Testing

Written by  John Boyle

This month’s Tailgate Topic covers the important task of no-voltage testing, sometimes referred to as absence of voltage testing or no-potential testing. No lineworker is ever excluded from the requirements of testing conductors to verify the absence of voltage when required, although methods and practices on how this is accomplished will vary among companies. The following is a basic overview of how to test both exposed conductors and cable. The steps provided here are demonstrative in nature and not intended to replace your local rules and procedures.

This Tailgate also covers the general work practices that should be performed when de-energizing conductors and equipment prior to commencing work on a de-energized basis. In all cases a no-voltage test must be performed using an approved testing device only. Ensure you verify the range of your testing equipment, determining that it will be capable of handling the voltage you are testing; all too often the wrong tester is used, resulting in unwanted consequences that include damaging your tester or – worse yet – creating an electrical flash.

No-Voltage Testing of Items Other Than Cable
The following procedure is a general outline for testing conductors and electrical equipment, other than cable, for no voltage.
1. Prove your meter operates on a known voltage source.
2. Check for voltage using a properly proven device approved for the voltage involved.
3. Verify no-voltage condition is indicated.
4. Prove your meter operates on a known voltage source.
5. Proceed with the work or with the installation of grounds as required.

No-Voltage Testing of Cable
The following procedure is a general outline for no-voltage testing on all types of cable except series street lighting cable. Specific instructions for metallic sheath, nonmetallic sheath and concentric neutral cables should be followed as defined by your company’s procedures and practices, as well as the manufacturer’s instructions for testing equipment being utilized.
1. Prove your meter operates on a known voltage source.
2. Bridge shielding before opening sheath.
3. Remove outer jacket or sheath, removing enough jacket to provide clearance between the testing device and the jacket or sheath.
4. Test for no voltage.
5. Verify no-voltage condition is indicated.
6. Remove all non-insulating materials or shielding layers around the entire circumference of the cable, providing ample clearance between the testing device and the shielding.
7. Test for no voltage after each step of shielding removal until the insulation is reached.
8. Verify no-voltage condition is indicated.
9. Test for no voltage on the insulation.
10. Verify no-voltage condition is indicated.
11. Check for stray voltage by testing from each conductor to ground with an approved low-voltage testing device.
12. Verify no-voltage condition is indicated.
13. Prove your meter operates on a known voltage source.

What If You Find Voltage?
When voltage is indicated and the testing device is proven using a known voltage source, no work must be performed or ground installed until the reason for the voltage indication has been identified and removed, or proven to be due to induction. Check the following as possible sources of voltage.
• Incorrect job location
• Incorrect blocking points that have been established including back-feed sources
• Contact with foreign voltage source
• Induced voltage from high-voltage conductors. When this condition is suspected, a voltmeter-type test device must be used to check phase-to-ground and phase-to-phase voltage.

Detailed instructions to be followed when unusual conditions are encountered should be available from your company.

Though these two examples are generic in nature, the intent is the same. No conductor can be considered de-energized unless it is first isolated from the system, tested for absence of voltage and then grounded. Until all these steps occur, all conductors must be treated as energized. By following these basic principles, you can assure your safety and the safety of your crew.

About the Author: John Boyle is vice president of safety and quality for INTREN, an electric, gas and telecommunication construction company based in Union, Ill. Boyle has more than 28 years of experience, and has worked in nuclear and wind power generation and electric and gas distribution.

Last modified on Monday, 17 October 2011 12:30

Leave a comment

FREE Subscription to iP Magazine.
We'll send you 6 issues a year at no charge!

Latest iP Articles


Behavior Safety Training for Safety Committee Members
Industries concerned about bottom-line expenses tend to place behavior safety training low on the priority list. However, consider the direct costs your company paid for incidents, accidents, injuries, lost time, lost produ...
Strategic Safety Partners
In 2004, the Occupational Safety and Health Administration (OSHA) entered into the Electrical Transmission & Distribution (ET&D) Strategic Partnership agreement with six electrical contractors: Asplundh Tree Expert ...
The Intersect: A Practical Guide to Work-Site Hazard Analysis
A hazard is essentially a condition or activity that, if left uncontrolled, may result in an accident or a serious injury. To effectively identify hazards, the observer must develop a means of recognizing a hazard exposure....
Integrity and Respect: Two of Our Most Important Tools
Few things are more difficult to establish or easier to lose than integrity. As safety professionals, if our workers, bosses and peers see us as people of integrity, we can ask things of them with a very real expectation th...
Keys to Effective Fall Protection
The electric utility industry is loaded with potential hazards. Climbing at heights is one of those inherent safety risks that come with the job. At Louisville Gas and Electric (LG&E) and Kentucky Utilities (KU), we req...

Most Popular Articles


Incident Analysis
The essence of safety is preventing incidents from having the opportunity to occur. When they do occur, it is usually the result of one or more safety systems failures. Failures, however, are the seeds of opportunity. Incid...
Top Five PPE Mistakes
Identifying PPE Mistakes in Electric Arc Flash Programs After a decade of electric arc testing, incident investigations and incident replications using electric arcs, a few lessons have emerged as critical in assessing a ...
When is a Lineman a Lineman?
This feature's title is not a rhetorical question. There really should be an answer-a definitive, widely accepted answer we could all give quickly and consistently. There isn't and we can't, though we try with great confide...
Effective Fall Protection for Utility Workers
A review of the relevant standards and training that companies need to provide. ...

Search

Tailgate Safety

Sign Up for Tailgate Safety E-Newsletter
Sponsors are Key to the Success of Incident Prevention
DBI Sala
Glove Guard
Institute for Safety in Powerline Construction - Lineman Safety and Training
Pelsue
Utility Jobs Online